gogo logo
  • Монгол
  • Yolo
  • Maamuu
  • Politics
  • Economy
  • Society
  • Life
  • Interview
  • Culture
  • TRAVEL
  • Ulaanbaatar
  • Media OutReach
Helpful
Interview
  • - Interview
Interesting
Other
Монгол
Maamuu
Yolo
Main menu
Politics
Economy
Society
Life
Interview
Culture
TRAVEL
Ulaanbaatar
Media OutReach
Helpful
Interview
Interview
Interesting
Other menu
Монгол
Maamuu
Yolo
Contact us
Editorial ethics
Home
Search
Menu
  Facebook   Twitter
  Menu
Home
/ Society
Society

Wind power projects in Mongolia

  Facebook   Tweet
  Facebook  Tweet

Wind power projects in Mongolia

40% of Mongolian territory is suitable for wind energy. There are several wind energy projects deploying this opportunity with private investment. A total capital investment of those projects mounts to nearly USD800M.

Salkhit wind farm project

70km away from UB city in Sergelen Soum, Tuv province, the project is operational wind farm of 49.6MW. Investors are Clean Energy LLC, Newcom LLC, General Electric of USA, EBRD, Netherlands Development Finance Company.
The total investment is approximately USD120M for the farm of 49.6MW which consists of 31 wind turbines (1.6MW each). 
Millenium Challenge Account has played critical role in the project financing the expansion of Nalaikh substation, UB-Nalaikh cable construction for improving NDC effectiveness in control and coordination, and supply of simulator for energy regime. 
General contractor of the project was Leighton and a total of 18 local su-contracctors participated in the construction process. Nearly 95% of the total peak constructiuon personnel was Mongolian employees.

Oyutolgoi wind farm project

Currenty, 250MW OT windfarm is the largest in its sort for Mongolia. 
2 staged project is implemented by Qleantech LLC. First 102MW capacity will be operational by 2016 and it will be connected to OT substation of CES. First stage capital investment equals USD200M and will flow in from Swedish and Chinese private investors.
102MW project will supply 360M kWh electricity, save 430,000t of coal, and supply electricity to nearly 300,00 households. 
Remaining 148MW or the 2nd stage of the project will be realized in the foreseeable future to supply China and further Super Grid of Asia.

Sainshand wind farm project

Located in northeastern Sainshand, Dornogobi, this project is 52MW and scheduled to be commissioned in 2015-2016. The chief investor is Ferrostaal of Germany. 
The project investment is USD120M and once the wind farm is operational, it should be able to supply 170M kWh of electricity per year to the CES. 
International tender for contractor selection was announced in July 2014. The wind farm will commission in second halt of 2016.

Choir wind farm project

Turkish invested Aydiner Global LLC is investing in a 50MW wind farm project located in Choir, Gobisumber province. A total of USD100M is estimated for capital investment and annual production and supply of electricity to the CES is estimated 140M kWh.

Clean Energy Asia LLC

Clean Energy LLC has acquired the special permit for 50MW wind farm construction in Tsogttsetsii, Umnugobi Province in October 2014 in alliance with Softbank and Newcom.

Source: www.monwea.org

40% of Mongolian territory is suitable for wind energy. There are several wind energy projects deploying this opportunity with private investment. A total capital investment of those projects mounts to nearly USD800M.

Salkhit wind farm project

70km away from UB city in Sergelen Soum, Tuv province, the project is operational wind farm of 49.6MW. Investors are Clean Energy LLC, Newcom LLC, General Electric of USA, EBRD, Netherlands Development Finance Company.
The total investment is approximately USD120M for the farm of 49.6MW which consists of 31 wind turbines (1.6MW each). 
Millenium Challenge Account has played critical role in the project financing the expansion of Nalaikh substation, UB-Nalaikh cable construction for improving NDC effectiveness in control and coordination, and supply of simulator for energy regime. 
General contractor of the project was Leighton and a total of 18 local su-contracctors participated in the construction process. Nearly 95% of the total peak constructiuon personnel was Mongolian employees.

Oyutolgoi wind farm project

Currenty, 250MW OT windfarm is the largest in its sort for Mongolia. 
2 staged project is implemented by Qleantech LLC. First 102MW capacity will be operational by 2016 and it will be connected to OT substation of CES. First stage capital investment equals USD200M and will flow in from Swedish and Chinese private investors.
102MW project will supply 360M kWh electricity, save 430,000t of coal, and supply electricity to nearly 300,00 households. 
Remaining 148MW or the 2nd stage of the project will be realized in the foreseeable future to supply China and further Super Grid of Asia.

Sainshand wind farm project

Located in northeastern Sainshand, Dornogobi, this project is 52MW and scheduled to be commissioned in 2015-2016. The chief investor is Ferrostaal of Germany. 
The project investment is USD120M and once the wind farm is operational, it should be able to supply 170M kWh of electricity per year to the CES. 
International tender for contractor selection was announced in July 2014. The wind farm will commission in second halt of 2016.

Choir wind farm project

Turkish invested Aydiner Global LLC is investing in a 50MW wind farm project located in Choir, Gobisumber province. A total of USD100M is estimated for capital investment and annual production and supply of electricity to the CES is estimated 140M kWh.

Clean Energy Asia LLC

Clean Energy LLC has acquired the special permit for 50MW wind farm construction in Tsogttsetsii, Umnugobi Province in October 2014 in alliance with Softbank and Newcom.

Source: www.monwea.org

  Facebook   Tweet
Category
Society
Published
2015-06-04


gogo logo
Contact us Editorial ethics

© 2007 - 2025 Mongol Content LLC