gogo logo
  • Монгол
  • Yolo
  • Maamuu
  • Politics
  • Economy
  • Society
  • Life
  • Interview
  • Culture
  • TRAVEL
  • Ulaanbaatar
  • Media OutReach
Helpful
Interview
  • - Interview
Interesting
Other
Монгол
Maamuu
Yolo
Main menu
Politics
Economy
Society
Life
Interview
Culture
TRAVEL
Ulaanbaatar
Media OutReach
Helpful
Interview
Interview
Interesting
Other menu
Монгол
Maamuu
Yolo
Contact us
Editorial ethics
Home
Search
Menu
  Facebook   Twitter
  Menu
Home
/ Society
Society

Construction process of new airport is at 56.8 percent

  Facebook   Tweet
 
Bloomberg TV Mongolia
2015-09-15
  Facebook  Tweet
 

Construction process of new airport is at 56.8 percent

Only 480 days left for the finish of New Ulaanbaatar International Airport construction project. The Project Implementation Unit reported that this year is considered as the peak period of the project.

They aimed to reach the construction performance to 65.8 percent within the end of 2015 by working with busy schedule and detailed planning. As of September 11th, the construction process is at 56.8 percent which over fulfilled the planned performance by 3.6 percent.

Currently, the concrete works of 2 runways, road and rail terminal have completed and interior works have started. Moreover, electrical, mechanical, telecommunications, security, security systems, network engineering moisture protection, fire protection system works are going underway.

As of today, more than 2100 staffs and engineers are working at the construction site while about 220 vehicles and techniques are operating at the site.

 

Only 480 days left for the finish of New Ulaanbaatar International Airport construction project. The Project Implementation Unit reported that this year is considered as the peak period of the project.

They aimed to reach the construction performance to 65.8 percent within the end of 2015 by working with busy schedule and detailed planning. As of September 11th, the construction process is at 56.8 percent which over fulfilled the planned performance by 3.6 percent.

Currently, the concrete works of 2 runways, road and rail terminal have completed and interior works have started. Moreover, electrical, mechanical, telecommunications, security, security systems, network engineering moisture protection, fire protection system works are going underway.

As of today, more than 2100 staffs and engineers are working at the construction site while about 220 vehicles and techniques are operating at the site.

 