Turquoise Hill Resources Ltd. released its 2017 third quarter report on November 2, 2017.
The Oyu Tolgoi underground development project spend totaled 1.9 billion USD in Q3'17. The project's Shaft II sinking has reached 1,249 meters and is expected to be completed by the end of the quarter.
Underground mine exploration will begin in 2020 with production set to begin in 2021. Operational cash costs equaled 161.9 million USD in Q3’17, a 17.7 percent decline over 2016. Sales reached 197.8 million USD, 8.9 million USD higher than the previous quarter. Ministry of Finance stated that increased content of gold concentrate at the Oyu Tolgoi mine could contribute to state revenue in 2017 and 2018.
HIGHLIGHTS
Oyu Tolgoi achieved an All Injury Frequency Rate of 0.25 per 200,000 hours worked for the nine months ended September 30, 2017.
During Q3’17, underground lateral development made good progress and since the re-start of development a total of 5.4 equivalent kilometres has been completed.
Shaft 2 sinking was at 1,249 metres at the end of Q3’17 and sinking is expected to be complete by the end of 2017 with fit out occurring over 2018.
During September 2017, the underground development team achieved the best sinking rate for Shaft 5 since project restart averaging 2.6 metres per day.
At the end of Q3’17, total underground project spend since re-start and capital commitments totaled $1.9 billion.
First draw bell is planned for mid-2020 and sustainable first production in 2021.
Oyu Tolgoi set three operational records during Q3’17 for total material mined, ore treated and average daily concentrator throughput.
Revenue of $246.9 million in Q3’17 increased 21.2% over Q2’17 reflecting higher copper and gold prices partly offset by lower concentrate sales.
Cash generated from operating activities before interest and taxes in Q3’17 was $94.7 million and $234.7 million year- to-date at the end of Q3’17.
In Q3’17, the Company recorded net income attributable to owners of Turquoise Hill of $65.3 million or $0.03 per share.
Copper production in Q3’17 was essentially flat compared to Q2’17 while gold production increased 29.2% over Q2’17 due to higher head grades from the medium-grade stockpile and Phase 4A.
For Q3’17, Oyu Tolgoi’s cost of sales was $2.43 per pound of copper sold; C1 cash costs were $1.83 per pound of copper produced and all-in sustaining costs were $2.76 per pound of copper produced1 .
Operating cash costs1 of $161.9 million for Q3’17 were relatively flat over Q2’17 while year-to-date operating cash costs of $494.0 million at the end of Q3’17 declined 17.7% over year-to-date Q3’16.
Turquoise Hill’s cash and cash equivalents at September 30, 2017 were approximately $1.5 billion.
Turquoise Hill Resources Ltd. released its 2017 third quarter report on November 2, 2017.
The Oyu Tolgoi underground development project spend totaled 1.9 billion USD in Q3'17. The project's Shaft II sinking has reached 1,249 meters and is expected to be completed by the end of the quarter.
Underground mine exploration will begin in 2020 with production set to begin in 2021. Operational cash costs equaled 161.9 million USD in Q3’17, a 17.7 percent decline over 2016. Sales reached 197.8 million USD, 8.9 million USD higher than the previous quarter. Ministry of Finance stated that increased content of gold concentrate at the Oyu Tolgoi mine could contribute to state revenue in 2017 and 2018.
HIGHLIGHTS
Oyu Tolgoi achieved an All Injury Frequency Rate of 0.25 per 200,000 hours worked for the nine months ended September 30, 2017.
During Q3’17, underground lateral development made good progress and since the re-start of development a total of 5.4 equivalent kilometres has been completed.
Shaft 2 sinking was at 1,249 metres at the end of Q3’17 and sinking is expected to be complete by the end of 2017 with fit out occurring over 2018.
During September 2017, the underground development team achieved the best sinking rate for Shaft 5 since project restart averaging 2.6 metres per day.
At the end of Q3’17, total underground project spend since re-start and capital commitments totaled $1.9 billion.
First draw bell is planned for mid-2020 and sustainable first production in 2021.
Oyu Tolgoi set three operational records during Q3’17 for total material mined, ore treated and average daily concentrator throughput.
Revenue of $246.9 million in Q3’17 increased 21.2% over Q2’17 reflecting higher copper and gold prices partly offset by lower concentrate sales.
Cash generated from operating activities before interest and taxes in Q3’17 was $94.7 million and $234.7 million year- to-date at the end of Q3’17.
In Q3’17, the Company recorded net income attributable to owners of Turquoise Hill of $65.3 million or $0.03 per share.
Copper production in Q3’17 was essentially flat compared to Q2’17 while gold production increased 29.2% over Q2’17 due to higher head grades from the medium-grade stockpile and Phase 4A.
For Q3’17, Oyu Tolgoi’s cost of sales was $2.43 per pound of copper sold; C1 cash costs were $1.83 per pound of copper produced and all-in sustaining costs were $2.76 per pound of copper produced1 .
Operating cash costs1 of $161.9 million for Q3’17 were relatively flat over Q2’17 while year-to-date operating cash costs of $494.0 million at the end of Q3’17 declined 17.7% over year-to-date Q3’16.
Turquoise Hill’s cash and cash equivalents at September 30, 2017 were approximately $1.5 billion.