D.Orosoo, Bayangol District Governor and Head of the Special Commission, made an official announcement on the situation raised at the 14th khoroo in Bayangol District.
During the annoucement he stated that although the evacuation costs were issued by the Reserve Fund of the Capital City, those will be refunded by the responsible parties.
The owner of the 18 storey building project in front of the apartment building 16 is BGBG LLC and they were authorized to do construction works by the license issued from the Ministry of Construction and Urban Deveopment dated July 22, 2014. Complaints from the residents led the governor of Bayangol District to send official letters to the responsible state entities. BGBG LLC initially received license to build parking lot back in 2008.
Representative of BGBG LLC attended the meeting and confirmed that the company will reimburse the costs associated with the evacuation, but requested time due to current financial difficulties. Therefore all the costs of the evacuation will be financed from the Reserve Fund of the Capital City as of now.
Moreover, the risky situation at the hole is to be treated with moulding according to Mr D.Orosoo. Capital City Special Commission meeting agreed to invalidate the construction license at the site.
D.Orosoo, Bayangol District Governor and Head of the Special Commission, made an official announcement on the situation raised at the 14th khoroo in Bayangol District.
During the annoucement he stated that although the evacuation costs were issued by the Reserve Fund of the Capital City, those will be refunded by the responsible parties.
The owner of the 18 storey building project in front of the apartment building 16 is BGBG LLC and they were authorized to do construction works by the license issued from the Ministry of Construction and Urban Deveopment dated July 22, 2014. Complaints from the residents led the governor of Bayangol District to send official letters to the responsible state entities. BGBG LLC initially received license to build parking lot back in 2008.
Representative of BGBG LLC attended the meeting and confirmed that the company will reimburse the costs associated with the evacuation, but requested time due to current financial difficulties. Therefore all the costs of the evacuation will be financed from the Reserve Fund of the Capital City as of now.
Moreover, the risky situation at the hole is to be treated with moulding according to Mr D.Orosoo. Capital City Special Commission meeting agreed to invalidate the construction license at the site.