"Norbu" and "Shimt Gazar" companies have accomplished planned renovation project of Selbe River and only lighting and benches are left for completion.
Renovation project was started with singing of an agreement on Aug 8, 2011 and was expected to be done by June 30, 2014.
According to agreement companies have completed 350 m renovation with starting point at Ikh Toiruu Bridge and ending at Golden Vill bridge. Projected MNT 2 billion budget was expanded by MNT 297.8 million to see project completion.
Initially this renovation projected 1.3 km with MNT 8.5 billion budget and it is up to city governing body whether to proceed with further renovation.
Unfortunately, there were litters all over the place and we call for UB residents to be considerate of our environment and build a better place for each other.
South of Golden Vill bridge. No refurbishing planned beyond this point
View from south
"Norbu" and "Shimt Gazar" companies have accomplished planned renovation project of Selbe River and only lighting and benches are left for completion.
Renovation project was started with singing of an agreement on Aug 8, 2011 and was expected to be done by June 30, 2014.
According to agreement companies have completed 350 m renovation with starting point at Ikh Toiruu Bridge and ending at Golden Vill bridge. Projected MNT 2 billion budget was expanded by MNT 297.8 million to see project completion.
Initially this renovation projected 1.3 km with MNT 8.5 billion budget and it is up to city governing body whether to proceed with further renovation.
Unfortunately, there were litters all over the place and we call for UB residents to be considerate of our environment and build a better place for each other.
South of Golden Vill bridge. No refurbishing planned beyond this point
View from south